This report provides a list of assets for which the meter is projected to reach its end of life within the specified date range and before the given start date. The report shows the Projected Replacement Costs for up to 5 years. Use this report to:
Identify projected replacement costs by year.
A detailed listing of assets of an organization including acquired and current meter readings, meter life expectancy, projected meter end of life and projected replacement costs for up to 5 years.
As needed to estimate meter replacement dates and replacement costs.
The Standard window opens.
In the Assets section, click W136 - Meter End Of Life Projection.
Required parameters are indicated by an *.
Click to schedule the report. For more information, refer to Scheduled Reports > Creating Scheduled Report.
Click to print the report in a PDF format.
Click to print the report.
This will generate a File dialogue box specific to your computer.